International Engineering Enterprise Laing O’Rourke required wetroom drainage solutions for their new 41 storey residential & mixed use tower.

The Challenge

Two Fifty One is a new build 41 storey residential & mixed use tower at the entry to Elephant & Castle, offering 335 apartments (studios, 1, 2 and 3 bedroom apartments) with great views of London’s skyline. The stunning development also features a 24 hour concierge service, gymnasium/health club, cinema, on-site café bar, restaurant and landscaped residents garden.
CCL Wetrooms were contacted by Laing O’Rourke to design and supply drainage solutions for 193 wetrooms in their luxury development of apartments. The wetrooms of similar sizes needed appropriate linear drainage for the shallow floor build up that could also achieve a very short run off from the waste pipe to the stack.

 

The Solution

Due to the shallow nature of the floor build ups within the high rise apartment complex, there was a need for appropriate low level drainage systems to be installed that could meet the shallow depth requirements and deliver a drainage solution in this restricted space.

CCL Wetrooms specified the installation of Linear Screed Drains with Solid Stainless Steel Grills into the apartments and penthouses, thanks to the drains’ minimal height of only 67mm. Laing O’Rourke were able to achieve a low level waste connection in the floor build-up of under 80mm and in order to ensure a short as possible run-off on the waste pipe to the stack, the drains were bespoke manufactured in left and right-handed versions. This requirement to manufacture the drain in a left or right handed version has resulted in CCL Wetrooms adding the left and right handed drain options to the range as standard.

Two Fifty One, Southwark Bridge Road
RIBA Logo BBA Logo

Testimonial

The Linear Screed Drain was an ideal system to install in into Two Fifty One Southwark Bridge Road, due to the shallow nature of the trap. CCL Wetrooms provided a very professional service and I found all aspects of the design, manufacture and delivery of the drains to the project to be highly efficient.